126 Phillip Street
Bathrooms, showers and a state of the art bike facilities were built into a confined basement loading dock to allow staff an alternative to commuting to the office by public transport or car. As part of the project the building security office was relocated to a new office built within the loading dock.
This stage of the project involved relocation of all building essential services BMS, FIP, Lift Control, Building Intercom. Girvan Group consulted all contractors prepared a detailed methodology outlining the best way to undertake the relocation with little minimum down time to the buildings operation. The relocation was successfully completed over two weekends.
All trades were managed by Girvan Group in construction with bespoke locker design with translucent doors and lighting, specialised signs, amenities, lockers, fire hydraulics, Metex metal cladding illuminated from behind, and the installation of a 2 tier push-bike arc and push-bike cradle.