Refurbishment
Location: Sydney
Client: Target
Client: Target
The Solution
Management of building approvals and alternate solutions.
Alternative D&C services design on hydraulic services and electrical to ensure budgets could be maintained.
Construction of new café and associated services.
80% of works completed at night to ensure minimal disruption to trading.
Management and coordination of target supplied items.
Completion Date
Week Turnaround
What our customers say
Find out what our customers had to say about their experience working with us.
“We were really impressed with Girvan Group’s commitment and professionalism in getting the job done. They went above and beyond to finish the project in an 8 week programme – a first for Target, with the usual programme lasting 14 weeks.”